Galeria Korona Kielce – works nearing completion

Galeria Korona Kielce

In the nearest week, Multikino will be able to move into Korona Kielce Shopping Centre. The delivery of this shopping and entertainment centre shall take place even before Easter. At the construction site, as well as in the office of the company responsible for commercialisation, things seem to speed up.

Currently, 380 people work at the construction site in the centre of Kielce; finishing works will be carried out by over 2 000 workers. The construction in the raw unfinished state is getting close to completion, final reinforced concrete works will last until the end of November.

“We are already on the last level; now we are doing the +2 level and the roof of the building. 30 percent of the roof have already been made. The entrance to car parks facing Polna Street and exits on the levels 1, 2 and 3 are completed, while the entrance facing Radiowa Street is finished in 80 percent,” says Stanisław Kowal, Contract Director at Korona Kielce.

Finishing works are underway on individual levels. On the -2 level, final installation works are carried out. All masonry works in raw state are nearing completion. Nine cinema rooms are being prepared for the needs of the tenant. Multikino will start moving in within the nearest few days, a squash club and a Pure fitness clubs will be next to come.

Libra Project, which is responsible for commercialisation of Korana Kielce, is also working intensively. Already, 70 percent of units have been let.